Planning & Quantity Surveying (QS) Engine

Master Schedules, Work Orders, RA Billing & Material Verification

Pending BOQ Scope Items
10
uncompleted packages
Balance Work Value
₹ 8.56 Cr
remaining BOQ value
Delayed Packages
3
requires acceleration
Avg Schedule Completion
40%
overall progress
Piling & Deep Foundations in-progress
Reinforcing Steel Cage Fabrication
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-07-03
Target Completion: 2026-07-28
Total Scope: 180 MT
Executed: 160 MT
Balance Work Qty:
20 MT ₹ 11,60,000
Execution Progress 89%
Piling & Deep Foundations in-progress
Piling Concrete Pouring
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-07-05
Target Completion: 2026-07-30
Total Scope: 1,200 CuM
Executed: 950 CuM
Balance Work Qty:
250 CuM ₹ 15,50,000
Execution Progress 79%
Piling & Deep Foundations not-started
Piling Excavation (25m depth)
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-02-20
Target Completion: 2026-07-31
Total Scope: 1,200 CuM
Executed: 0 CuM
Balance Work Qty:
1,200 CuM ₹ 2,64,00,000
Execution Progress 0%
Piling & Deep Foundations in-progress
Reinforcing Steel Cage Fabrication
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-07-02
Target Completion: 2026-07-28
Total Scope: 180 MT
Executed: 165 MT
Balance Work Qty:
15 MT ₹ 8,70,000
Execution Progress 92%
Piling & Deep Foundations not-started
Piling Concrete Pouring
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-02-20
Target Completion: 2026-07-31
Total Scope: 1,200 CuM
Executed: 0 CuM
Balance Work Qty:
1,200 CuM ₹ 79,20,000
Execution Progress 0%
Substructure & Piers started
Pile Cap Concrete
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-07-15
Target Completion: 2026-08-15
Total Scope: 850 CuM
Executed: 420 CuM
Balance Work Qty:
430 CuM ₹ 30,53,000
Execution Progress 49%
Substructure & Piers started
Pier Pedestal Fabrication
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-07-18
Target Completion: 2026-08-20
Total Scope: 95 MT
Executed: 30 MT
Balance Work Qty:
65 MT ₹ 39,00,000
Execution Progress 32%
Substructure & Piers delayed
Pier Column Casting
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-07-20
Target Completion: 2026-08-30
Total Scope: 600 CuM
Executed: 120 CuM
Balance Work Qty:
480 CuM ₹ 37,44,000
Execution Progress 20%
Reason for Delay
RMC batching plant conveyor breakdown caused 4-day pour halt.
Substructure & Piers not-started
Pile Cap Concrete
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-02-20
Target Completion: 2026-07-31
Total Scope: 850 CuM
Executed: 0 CuM
Balance Work Qty:
850 CuM ₹ 61,33,600
Execution Progress 0%
Substructure & Piers not-started
Pier Pedestal Fabrication
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-08-01
Target Completion: 2026-08-25
Total Scope: 95 MT
Executed: 0 MT
Balance Work Qty:
95 MT ₹ 57,00,000
Execution Progress 0%
Substructure & Piers not-started
Pier Column Casting
Sub-Contractor: Star Bar-Bending Works (SCWO/STAR/042)
Date Assigned: 2026-02-20
Target Completion: 2026-07-31
Total Scope: 600 CuM
Executed: 0 CuM
Balance Work Qty:
600 CuM ₹ 47,52,000
Execution Progress 0%
Substructure & Piers not-started
Substructure Finishing Works
Sub-Contractor: Apex Structural Sub-Contractors (SCWO/APEX/088)
Date Assigned: 2026-08-10
Target Completion: 2026-09-10
Total Scope: 1,000 SqM
Executed: 0 SqM
Balance Work Qty:
1,000 SqM ₹ 22,00,000
Execution Progress 0%
Adyar Block B Structure Core in-progress
Post-Tensioned Slab Casting
Sub-Contractor: Vanguard Piling Rigs (SCWO/VANG/015)
Date Assigned: 2026-07-10
Target Completion: 2026-07-31
Total Scope: 1,400 CuM
Executed: 1,100 CuM
Balance Work Qty:
300 CuM ₹ 21,60,000
Execution Progress 79%
Adyar Block B Structure Core delayed
Anchorage Installation
Sub-Contractor: Vanguard Piling Rigs (SCWO/VANG/015)
Date Assigned: 2026-07-18
Target Completion: 2026-08-10
Total Scope: 150 Nos.
Executed: 45 Nos.
Balance Work Qty:
105 Nos. ₹ 3,25,500
Execution Progress 30%
Reason for Delay
Port customs clearance hold for imported anchorage castings.
Adyar Block B Structure Core not-started
Concrete Core Walls
Sub-Contractor: Vanguard Piling Rigs (SCWO/VANG/015)
Date Assigned: 2026-08-05
Target Completion: 2026-09-15
Total Scope: 1,200 CuM
Executed: 0 CuM
Balance Work Qty:
1,200 CuM ₹ 96,00,000
Execution Progress 0%