Pier Connecting & Substructure Formwork
| SR. NO | BOQ ITEM NAME (FROM CLIENT WO) | SPECIFICATION DESCRIPTION | UNIT | CLIENT QTY | CLIENT RATE | SUB QTY | SUB RATE (₹) | SUB AMOUNT (₹) | ALLOCATION REMARKS |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PILING & DEEP FOUNDATIONS | ||||||||
| — | Piling Excavation (25m depth) | Bored cast-in-situ piling using bentonite slurry | CuM | 1,200 | ₹25,000 |
₹
|
₹27,000,000 | ||
| — | Reinforcing Steel Cage Fabrication | Fe 550D TMT reinforcement steel bars | MT | 180 | ₹65,000 |
₹
|
₹10,530,000 | ||
| — | Piling Concrete Pouring | M35 Grade high-slump tremie concrete | CuM | 1,200 | ₹15,000 |
₹
|
₹8,550,000 | ||
| — | Sonic Integrity Testing | Cross-hole sonic logging tests on piles | Nos. | 12 | ₹5,000 |
₹
|
₹28,800 | ||
| 2 | SUBSTRUCTURE & PIERS | ||||||||
| — | Pile Cap Concrete | M40 Grade structural concrete | MT | 95 | ₹68,000 |
₹
|
₹6,080,000 | ||
| — | Pier Pedestal Fabrication | Reinforcing steel and template alignment | MT | 95 | ₹68,000 |
₹
|
₹6,080,000 | ||
| — | Pier Column Casting | M45 Grade self-compacting concrete | CuM | 600 | ₹9,000 |
₹
|
₹4,680,000 | ||
| GRAND TOTAL WORK ORDER VALUE | ₹61,100,000 | ||||||||
Girder Erection & Deck Slab Casting
| SR. NO | BOQ ITEM NAME (FROM CLIENT WO) | SPECIFICATION DESCRIPTION | UNIT | CLIENT QTY | CLIENT RATE | SUB QTY | SUB RATE (₹) | SUB AMOUNT (₹) | ALLOCATION REMARKS |
|---|---|---|---|---|---|---|---|---|---|
| 1 | ELEVATED GIRDER LAUNCHING | ||||||||
| — | Precast Girder Launching | Precast prestressed concrete box girders | Nos. | 48 | ₹1,250,000 |
₹
|
₹52,800,000 | ||
| — | Deck Slab Work | M40 grade reinforced concrete | CuM | 420 | ₹18,000 |
₹
|
₹4,950,000 | ||
| GRAND TOTAL WORK ORDER VALUE | ₹52,400,000 | ||||||||
Post-Tensioned Slab & Structural Concrete
| SR. NO | BOQ ITEM NAME (FROM CLIENT WO) | SPECIFICATION DESCRIPTION | UNIT | CLIENT QTY | CLIENT RATE | SUB QTY | SUB RATE (₹) | SUB AMOUNT (₹) | ALLOCATION REMARKS |
|---|---|---|---|---|---|---|---|---|---|
| 1 | POST-TENSIONED SLAB | ||||||||
| — | PT Slab System | PT slab system with high tensile strands | SqM | 1,800 | ₹7,200 |
₹
|
₹11,700,000 | ||
| 2 | STRUCTURAL CONCRETE | ||||||||
| — | Structural Concrete | M40 Grade structural concrete | CuM | 360 | ₹15,000 |
₹
|
₹4,860,000 | ||
| GRAND TOTAL WORK ORDER VALUE | ₹19,200,000 | ||||||||
Flow items directly from selected Client Work Order BOQ
| SR. | BOQ ITEM DESCRIPTION | UNIT | SUB QTY | SUB RATE (₹) | AMOUNT (₹) | REMARKS |
|---|---|---|---|---|---|---|
| GRAND TOTAL WORK ORDER VALUE | ||||||