Planning & Quantity Surveying (QS) Engine

Master Schedules, Work Orders, RA Billing & Material Verification

DPR-QS-01 2026-07-22
Concreting Pier Cap #12
Cube samples collected. Slump test 110mm verified.
Location: Pier P-45 Site
Achieved: 85 Cu.m
Verified By: J. Swamy (Senior QS)
DPR-QS-02 2026-07-21
Rebar Inspection & Binding
Minor delay due to 1hr rain. Rebar spacing approved.
Location: Adyar Yard B
Achieved: 18 MT
Verified By: M. Anand (Planning Eng)